Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 274: 1996-040-00 EXP UC COHO O&M, M&E & UC SCS/STH ACCLIMATION
Project Number:
Title:
Upper Columbia Production
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Methow 40.00%
Wenatchee 60.00%
Contract Number:
56662 REL 274
Contract Title:
1996-040-00 EXP UC COHO O&M, M&E & UC SCS/STH ACCLIMATION
Contract Continuation:
Previous: Next:
56662 REL 251: 1996-040-00 EXP MID-C COHO O&M, M&E & UC SCS/STH ACCLIMATION
  • 56662 REL 302: 1996-040-00 EXP UC COHO O&M, M&E & UC SCS/STH ACCLIMATION
Contract Status:
Issued
Contract Description:
FY23 marks the 4th year of Upper Columbia project mergers into 1996-040-00 (Mid-Columbia Reintroduction Feasibility Study), 2008-458-00 (Steelhead Kelt Reconditioning) and 2009-001-00 (Upper Columbia Spring Chinook and Steelhead Acclimation. This action creates administrative efficiencies within the Yakama Nation FRM, streamlining reporting, assets and funds for similar Basin actions to meet anadromous reintroduction objective goals.

This contract period from Feb. 1, 2023 through Jan. 31, 2024 would continue programmatic objectives for the coho reintroduction program. Duties to include primary O&M activities such as acclimation, adult collections and spawning and early egg incubation in both the Methow and Wenatchee basins will continue. Other actions are included as well (e.g.- carcass out planting, etc.) but are part of these overarching program goals and objectives. The Methow program will enter into its first year of Natural Production Phases (NPP 1) transitioning towards natural production; a decrease by 30% of the production down to 700,000 will be released from targeted tributaries (i.e.-Chewuch R., Twisp R., and Upper Methow R.).  The Wenatchee program continues to work through the Broodstock Development Phase Two (BDPII) of the program and will look to repeat project-specific studies to try and determine if a contingency can be implemented if adults are unable to ascend Tumwater Canyon at the rate required to meet BDPII objectives.

O&M activities to include: fish rearing/acclimation, broodstock collection, spawning, incubation, transportation of eyed eggs to LCR facilities, facility oversight/operations, annual non-technical production reporting (both in WEN and MET but also to include rearing summaries through USFWS subcontracting).  

M&E activities include survival measures and data collection for status and trend analyses of the coho program; both within year and for long-term comparisons. Coho abundance and egg-to-immigrant survival (through the use of smolt traps) for naturally produced juveniles on both Nason Creek as well as the lower Wenatchee River trap (operated by WDFW) allows for us to calculate smolt-to-adult rates for natural origin returns.  Hatchery in-pond acclimation survival as well as out-migrant run timing is critical in determining that volitional releases are the most appropriate means for releases of coho in both Methow and Wenatchee basins.   On the adult returns, escapement methods to be calculated will involve spawning ground surveys to determine spawning timing, distribution and H vs. N origin compositions.

M&E Activities covered under this contract would relate to tagging/marking of juveniles in the form of:
- CWT'ing/Body Tagging/PBT analysis/PIT tagging (the first 3 would provide information in determining SARs and the last one would be for in-pond and Columbia corridor survivals as juveniles)
- Data analysis for adult distribution, run composition, spawning densities and locations, MvsF ratios, run timing, fecundity, etc.  (activities to contribute to this would occur on spawning ground surveys and at spawning).
- Juvenile run timing, out-migration survival and abundance (via the rotary screw trap on Nason Cr. as well as the WDFW operated Cashmere screw tap)
- Program will include Cost-Sharing with Chelan and Grant County PUD  

The Spring Chinook and Steelhead acclimation distribution in the upper Methow where adult management is in place and being implemented to restrict/reduce hatchery influence and more importantly reduce the effects of a single source release location, which YN identified in the UCSCSA original plan. Currently, restrictions to the numbers being released in the upper Methow are due to the uncertainties of whether these decreases in productivity form the egg-to-emigrant life stage is due to super saturation in the reaches near Methow SFH and Winthrop NFH, hatchery contributions that are driving down reproductive success or a combination of both. The 2023 releases will include Chewuch AF and Goat Wall, used for acclimation of spring Chinook.  Steelhead in the Methow are being planned for release either from Early Winters, Mid-Valley-Pond and/or Gold Creek Ponds.  

This merged acclimation project proposes to further develop acclimation for upper Columbia steelhead and spring Chinook by developing new semi-natural ponds similar to what has been uniquely successful in the Mid-Columbia Coho Restoration Project. This would involve utilizing the existing PUD/Federal mitigation production in the region that is currently doing either direct stream plants or single point, large releases and expand/refine those releases by adding additional acclimation releases in known habitat reaches within the Wenatchee and Methow watersheds. This strategy will enhance the goals of recovery for these 2 listed stocks as discussed below.   Steelhead releases planned at the Powerline Pond site on upper Nason Creek is being planned for 2023.  
Account Type(s):
Expense
Contract Start Date:
02/01/2023
Contract End Date:
01/31/2024
Current Contract Value:
$2,991,650
Expenditures:
$2,393,320

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Rick Alford Yakama Confederated Tribes Yes Technical Contact alfr@yakamafish-nsn.gov (509) 996-9857
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Mary Haight Bonneville Power Administration Yes COR mthaight@bpa.gov (503) 230-3112
Tana Hoptowit Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Cory Kamphaus Yakama Confederated Tribes Yes Contract Manager kamc@yakamafish-nsn.gov (509) 548-9413x102
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Eric McOmie Bonneville Power Administration Yes Backup COR ermcomie@bpa.gov (503) 230-4964
Keely Murdoch Yakama Confederated Tribes Yes Interested Party murk@yakamafish-nsn.gov (509) 548-2206
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023
Thomas Scribner Yakama Confederated Tribes Yes Supervisor scrt@yakamafish-nsn.gov (503) 331-9850
Shawn Skinner Bonneville Power Administration Yes Env. Compliance Lead srskinner@bpa.gov (503) 230-3727
Shanita Sohappy Yakama Confederated Tribes No Administrative Contact sohsh@yakamafish-nsn.gov (509) 865-5121
Gregory Wolfe Yakama Confederated Tribes Yes Technical Contact wolg@yakamafish-nsn.gov (509) 881-0674
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Maintain and improvement existing/used hatchery O&M infrastructure A: 61. O&M for maintenance of facilities 01/31/2024
Eyed egg incubation & transportation for MCCRP program B: 66. Transport BY23 Coho eyed-eggs from incubation facilities to rearing facilities 01/31/2024
Coho broodstock collections-Methow and Wenatchee programs C: 66. Trap 2023 Coho broodstock at Dryden, Tumwater, Wells Dam (east and west ladders), Methow FH, Winthrop NFH, and Leavenworth NFH (backup site only) 12/15/2023 12/11/2023
Trinity Pilot Project and preparation for contracting/construction D: 115. Trinity Site Development for spring Chinook & coho 06/01/2023 06/08/2023
Effective implementation management and timely contract administration E: 119. Manage and Administer 2023-2024 Project for Mid Columbia Coho Restoration & Upper Columbia Spring Chinook and Steelhead known as Upper Columbia Production Projects 01/31/2024
Completed Annual Report F: 132. Finalize annual reporting of the CY22 period (2/1/22 through 1/31/23) 01/31/2024
Produce accessible, error-checked datasets G: 157. Analyze genetic tissue samples for PBT analysis of parental groups 01/31/2024
Produce accessible, error-checked datasets H: 157. Collect/Generate Field and Lab Data to determine 2023 emergence timing, growth and distribution 01/31/2024
Produce accessible, error-checked datasets I: 157. Extract CWT from 2023 brood coho snouts collected at spawning and on spawning ground surveys 01/31/2024
Produce accessible, error-checked datasets J: 157. Collect biological data from 2023 coho brood at spawning 01/31/2024
Produce accessible, error-checked datasets K: 157. Conduct spawning ground surveys for the 2023 return year in the Methow Basin 01/31/2024
Produce accessible, error-checked datasets L: 157. Conduct spawning ground surveys for the 2023 return year in the Wenatchee Basin 01/31/2024
Goat Wall release study PIT tagged fish M: 158. PIT tag up to 12,000 BY22 Spring Chinook in the Methow basin for 2023 releases 11/30/2023 11/15/2023
Methow and Wenatchee acclimated PIT tagged juveniles N: 158. Mark/Tag Animals - PIT-tag up to 80,000 BY22 coho pre-smolts 01/31/2024
CWT & PBT marking of MCCRP O: 158. Mark/Tag Animals - Subcontract CWT and/or PBT of approximately 1,700,000 BY22 coho pre-smolts 11/30/2023 12/18/2023
Coho database management for MCCRP P: 160. Enter data into and maintain local databases 01/31/2024
Deliverable: An accessible, error-checked data set with metadata Q: 162. Analyze and interpret M&E data from 2023 01/31/2024
Produce Environmental Compliance documents R: 165. Revise/Update Environmental Compliance Documentation for all applicable work on Coho Reintroduction and UCSCSA final site list compliance for acclimation 01/31/2024
Produce Hatchery Ops Plan S: 174. Hatchery Operations and Facility Plans 01/31/2024
Produce/Update Plan T: 174. Update Upper Columbia Spring Chinook & Steelhead Acclimation (UCSCSA) Plan as sites become identified as part of the implementation schedule 01/31/2024
Coho spawning at Winthrop NFH U: 176. Spawn 2023 brood coho at Winthrop NFH 12/30/2023 12/28/2023
Wenatchee program spawning @ LNFH V: 176. Spawn 2023 brood coho at Leavenworth NFH 12/25/2023 12/21/2023
Spring Chinook acclimation at Goat Wall W: 176. Acclimate BY21 Spring Chinook at Goat Wall Pond 05/30/2023 05/30/2023
Coho acclimation at Twisp Weir pond X: 176. Acclimation/Release Coho BY2021: Methow: Twisp Weir 05/01/2023 05/01/2023
Coho acclimation at Chewuch AP Y: 176. Acclimation/Release Coho BY2021: Methow: Chewuch Acclimation Facility 05/05/2023 05/05/2023
Coho acclimation at Mid Valley Pond Z: 176. Acclimation/Release Coho BY2021: Methow: Mid Valley Ponds 06/01/2023 06/01/2023
Coho acclimation at Early Winters Ponds AA: 176. Acclimation/Release Coho BY2021: Methow: Early Winters 06/01/2023 06/01/2023
Coho acclimation at Lower Twisp Ponds AB: 176. Acclimation/Release Coho BY2021: Methow: Lower Twisp Ponds 05/15/2023 05/15/2023
Coho acclimation at Eightmile Ranch Pond AC: 176. Acclimation/Release Coho BY2021: Methow: Eightmile Ranch 06/15/2023 06/15/2023
Coho acclimation at Leavenworth NFH AD: 176. Release Coho BY2021: Wenatchee: Leavenworth NFH 04/25/2023 04/25/2023
Coulter Pond acclimated coho releases-Wenatchee River Basin AE: 176. Acclimation/Release Coho BY2021: Wenatchee: Coulter pond 06/30/2023 06/30/2023
Butcher Creek acclimation of coho smolts AF: 176. Acclimation/Release Coho BY2021: Wenatchee: Butcher pond 06/30/2023 06/30/2023
Acclimate and volitional release coho at Rohlfing's Pond AG: 176. Acclimation/Release Coho BY2021: Wenatchee: Rohlfing's pond 06/30/2023 06/30/2023
Acclimate/volitional release of Beaver Creek Acclimation Pond-Wenatchee River Basin AH: 176. Acclimation/Release Coho BY2021: Wenatchee: Beaver Creek pond 06/30/2023 06/30/2023
Watershed Coordination on project implementation AJ: 191. Coordination of Plan with Regional Stakeholders 01/31/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 115 Produce Inventory or Assessment
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 158 Mark/Tag Animals
Coho (O. kisutch) - Unspecified Population
  • 13 instances of WE 176 Produce Hatchery Fish
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 174 Produce Plan
  • 6 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 115 Produce Inventory or Assessment
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 115 Produce Inventory or Assessment

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 61 O&M for maintenance of facilities 12/01/2022
B 66 Transport BY23 Coho eyed-eggs from incubation facilities to rearing facilities 12/01/2022
C 66 Trap 2023 Coho broodstock at Dryden, Tumwater, Wells Dam (east and west ladders), Methow FH, Winthrop NFH, and Leavenworth NFH (backup site only) 12/01/2022
D 115 Trinity Site Development for spring Chinook & coho 12/01/2022
E 119 Manage and Administer 2023-2024 Project for Mid Columbia Coho Restoration & Upper Columbia Spring Chinook and Steelhead known as Upper Columbia Production Projects
F 132 Finalize annual reporting of the CY22 period (2/1/22 through 1/31/23)
G 157 Analyze genetic tissue samples for PBT analysis of parental groups 12/01/2022
H 157 Collect/Generate Field and Lab Data to determine 2023 emergence timing, growth and distribution 12/01/2022
I 157 Extract CWT from 2023 brood coho snouts collected at spawning and on spawning ground surveys 12/01/2022
J 157 Collect biological data from 2023 coho brood at spawning 12/01/2022
K 157 Conduct spawning ground surveys for the 2023 return year in the Methow Basin 12/01/2022
L 157 Conduct spawning ground surveys for the 2023 return year in the Wenatchee Basin 12/01/2022
M 158 PIT tag up to 12,000 BY22 Spring Chinook in the Methow basin for 2023 releases 12/01/2022
N 158 Mark/Tag Animals - PIT-tag up to 80,000 BY22 coho pre-smolts 12/01/2022
O 158 Mark/Tag Animals - Subcontract CWT and/or PBT of approximately 1,700,000 BY22 coho pre-smolts 12/01/2022
P 160 Enter data into and maintain local databases
Q 162 Analyze and interpret M&E data from 2023
R 165 Revise/Update Environmental Compliance Documentation for all applicable work on Coho Reintroduction and UCSCSA final site list compliance for acclimation
S 174 Hatchery Operations and Facility Plans 12/01/2022
T 174 Update Upper Columbia Spring Chinook & Steelhead Acclimation (UCSCSA) Plan as sites become identified as part of the implementation schedule 12/01/2022
U 176 Spawn 2023 brood coho at Winthrop NFH 12/01/2022
V 176 Spawn 2023 brood coho at Leavenworth NFH 12/01/2022
W 176 Acclimate BY21 Spring Chinook at Goat Wall Pond 12/01/2022
X 176 Acclimation/Release Coho BY2021: Methow: Twisp Weir 12/01/2022
Y 176 Acclimation/Release Coho BY2021: Methow: Chewuch Acclimation Facility 12/01/2022
Z 176 Acclimation/Release Coho BY2021: Methow: Mid Valley Ponds 12/01/2022
AA 176 Acclimation/Release Coho BY2021: Methow: Early Winters 12/01/2022
AB 176 Acclimation/Release Coho BY2021: Methow: Lower Twisp Ponds 12/01/2022
AC 176 Acclimation/Release Coho BY2021: Methow: Eightmile Ranch 12/01/2022
AD 176 Release Coho BY2021: Wenatchee: Leavenworth NFH 12/01/2022
AE 176 Acclimation/Release Coho BY2021: Wenatchee: Coulter pond 12/01/2022
AF 176 Acclimation/Release Coho BY2021: Wenatchee: Butcher pond 12/01/2022
AG 176 Acclimation/Release Coho BY2021: Wenatchee: Rohlfing's pond 12/01/2022
AH 176 Acclimation/Release Coho BY2021: Wenatchee: Beaver Creek pond 12/01/2022
AI 185 Periodic Status Reports for BPA
AJ 191 Coordination of Plan with Regional Stakeholders